Question No.81

You have raised the issue that improving the testing process is also dependent on the status of the software development process. Which of the following phases in the fundamental test process is considered to deliver a document which can be used as a major input for test process improvement?

  1. Test planning and control

  2. Test implementation amp; execution

  3. Evaluating exit criteria and reporting

  4. Test project closure

Correct Answer: D

Question No.82

A software house is concerned about the number of defects found in software released to its customers. They are starting to plan a new software product. In the past, releases have often been stopped due to poor planning and too many defects found during high level testing. You have been recruited to the newly created position of test manager and asked to develop a test strategy, manage the testing of the project and organize the resources needed to carry out the testing. Which THREE activities would be valid steps during the development of the test strategy?

  1. Identify test staff members that will be involved in the system test

  2. Define test career paths

  3. Understand the software development life cycle used by the software house

  4. Assess the testing that needs to be done to minimize the risks

  5. Issue the test strategy document for review

  6. Define a master test plan template

  7. Perform a project risk analysis

Correct Answer: CDE

Question No.83

A software house is concerned about the number of defects found in software released to its customers. They are starting to plan a new software product. In the past, releases have often

been stopped due to poor planning and too many defects found during high level testing. You have been recruited to the newly created position of test manager and asked to develop a test strategy, manage the testing of the project and organize the resources needed to carry out the testing. As part of the test strategy, entry and exit criteria will be defined for each test level. Which is NOT a valid reason for using entry and exit criteria?

  1. The expectation is that development testing is not adequate.

  2. Exit criteria are used to decide on when to stop testing.

  3. Entry and exit criteria are a principal way for getting adequate resources.

  4. Using entry and exit criteria will prevent software that is not or poorly tested from going to the next test level.

Correct Answer: C

Question No.84

A software house is concerned about the number of defects found in software released to its customers. They are starting to plan a new software product. In the past, releases have often been stopped due to poor planning and too many defects found during high level testing. You have been recruited to the newly created position of test manager and asked to develop a test strategy, manage the testing of the project and organize the resources needed to carry out the testing. Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

  1. Any deviation from the procedures described in the test strategy document

  2. The overall estimated costs, timescales and resource requirements

  3. A detailed schedule of testing activities

  4. The development deliverables to be tested

  5. Which test staff members (names) will be involved and when

  6. Level of requirements coverage achieved

Which THREE of the above mentioned characteristics relate to the master test plan?

  1. a

  2. b

  3. c

  4. d

  5. e

  6. f

Correct Answer: ABD

Question No.85

A software house is concerned about the number of defects found in software released to its customers. They are starting to plan a new software product. In the past, releases have often been stopped due to poor planning and too many defects found during high level testing. You have been recruited to the newly created position of test manager and asked to develop a test strategy, manage the testing of the project and organize the resources needed to carry out the testing.

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

  1. Any deviation from the procedures described in the test strategy document

  2. The overall estimated costs, timescales and resource requirements

  3. A detailed schedule of testing activities

  4. The development deliverables to be tested

  5. Which test staff members (names) will be involved and when

  6. Level of requirements coverage achieved

Which TWO of the above mentioned characteristics relate to the phase test plan?

  1. a

  2. b

  3. c

  4. d

  5. e

  6. f

Correct Answer: BC

Question No.86

A software house is concerned about the number of defects found in software released to its customers. They are starting to plan a new software product. In the past, releases have often been stopped due to poor planning and too many defects found during high level testing. You have been recruited to the newly created position of test manager and asked to develop a test strategy, manage the testing of the project and organize the resources needed to carry out the testing. You are examining a document which gives the precise steps needed in order to execute a test. What is the correct definition of this document?

  1. Test design specification

  2. Test condition

  3. Test procedure specification

  4. Test case specification

Correct Answer: C

Question No.87

A software house is concerned about the number of defects found in software released to its customers. They are starting to plan a new software product. In the past, releases have often been stopped due to poor planning and too many defects found during high level testing. You have been recruited to the newly created position of test manager and asked to develop a test strategy, manage the testing of the project and organize the resources needed to carry out the testing. Which of the following would NOT be a common metric used for monitoring test preparation and execution?

  1. Number of Test cases passed and failed

  2. Percentage of planned test cases designed

  3. Number of test plan review comments

  4. Percentage of tasks complete in test environment preparation

Correct Answer: B

Question No.88

A software house is concerned about the number of defects found in software released to its customers. They are starting to plan a new software product. In the past, releases have often been stopped due to poor planning and too many defects found during high level testing. You have been recruited to the newly created position of test manager and asked to develop a test strategy, manage the testing of the project and organize the resources needed to carry out the

testing. Which of the following would you NOT expect to see on an incident report from test execution?

  1. The version(s) of the software under test

  2. The test execution schedule

  3. Expected results and actual results

  4. Precise steps to reproduce the problem

Correct Answer: B

Question No.89

A software house is concerned about the number of defects found in software released to its customers. They are starting to plan a new software product. In the past, releases have often been stopped due to poor planning and too many defects found during high level testing. You have been recruited to the newly created position of test manager and asked to develop a test strategy, manage the testing of the project and organize the resources needed to carry out the testing. Which of the following is NOT a valid use of decision coverage?

  1. Checking that all decisions have been exercised in a single program

  2. Checking that all decisions have been exercised in a business process

  3. Checking that all calls from one program module to another have been made correctly

  4. Checking that at least 50% of decisions have been exercised by a test case suite

Correct Answer: D

Question No.90

A software house is concerned about the number of defects found in software released to its customers. They are starting to plan a new software product. In the past, releases have often been stopped due to poor planning and too many defects found during high level testing. You have been recruited to the newly created position of test manager and asked to develop a test strategy, manage the testing of the project and organize the resources needed to carry out the testing. Which option BEST describes how the level of risk is determined?

  1. The likelihood of an adverse event happening multiplied by the cost of preventing it

  2. The consequences of a potential problem multiplied by the cost of possible legal action

  3. The impact of an adverse event multiplied of that event occurring

  4. The likelihood and the probability of a hazard occurring

Correct Answer: C